STAGE 1 : SUB-BASE AND DRAINAGE
a) The ground base should be inspected first for its suitability and will be shaped as fishback and well compacted. b) Drainage canals will be excavated in shape of fishbone, and main canals will be excavated alongside of the field with a specific slope. c) Geotextile felt will be laid in the canals and after fitting the drainage pipes on sand pillows the felt will be folded on the pipes. d) The canals will be filled with gravel e) To collect the waste waters one main and four small hollows will be digged. f) To water the field, water tank and springs will be established. g) The gravel will be smoothly levelled with a proper slope. h) The levelled base will be compated well to be finally ready for grass installation.
STAGE 2 : ARTIFICIAL TURF
a) The gravel surface will be entirely covered by felt. b) The turf carpets will be spread out on the felt. c) The carpets wil be joined on a seaming tape with the help of a special adhesive d) The adhesive is a double component polyurathane glue. e) The white or yellow lines will be fixed as per approved dimensions. Optionally the surface outside playing area may be red color. f) The grass carpet will be filled with silica sand by special machinary. g) The granule will be filled on sand by special machinary.